1 · Package document set

Every submittal package includes these, in this order.

  • Cover sheet — project, submittal number, spec section(s), date, and the submitting company
  • Transmittal — item list keyed to the schedule, with the reviewer/GC and the type (partial or full)
  • Table of contents / section dividers so the reviewer can navigate
  • Product data — manufacturer cut sheets marked to the exact model, options, and finish being furnished (strike what doesn't apply)
  • Shop drawings for anything fabricated or custom, matched to the drawings and schedules
  • Samples or physical mock-ups where the specification requires visual approval
  • Certifications & test reports the spec calls up (listings, ratings, compliance letters)
  • O&M data and warranties where required at this stage
  • Substitution request forms for any product not on the approved-manufacturer list

2 · Insulation & Firestopping scope — by spec section

Pull a submittal for each section in your scope; confirm the spec's Part 1 list.

  • Insulation product data for each type: R-value, thickness, facing, and where it is used (walls, roof, below slab, continuous insulation)
  • Fire test data for insulation, such as flame spread and smoke ratings, and the thermal barrier needed over exposed foam
  • Vapor retarder and accessory data where the spec calls for them
  • A firestop schedule listing every penetration and joint type: wall or floor type, rating, and what passes through (pipe material and size, cable, duct)
  • The tested system drawing for each condition on the schedule, from a recognized listing
  • Engineering judgments from the maker for any condition with no tested system
  • Product data for each firestop sealant, wrap, collar and device used in those systems
  • Installer qualifications and the inspection plan where the spec requires them

3 · Before you submit — common rejection reasons to rule out

Reviewers flag these first. Verify each is not an issue before you send.

  • Firestop product data with no tested system drawings
  • Tested systems that do not match the real wall or floor type, item size or rating
  • Penetrations from some trades missing from the firestop schedule
  • Engineering judgments missing, or not from the maker
  • Products from different firestop makers mixed within one system
  • Insulation without R-value or fire test data
  • Exposed foam insulation without the required thermal barrier

Free checklist from Submittal.app — the AI builder that assembles the whole package for you. submittal.app

Skip the checklist — let the AI build the package

Describe your insulation & firestopping scope or upload the spec section. Submittal.app finds the cut sheets, assembles the package with a cover and transmittal, and lets you refine it in chat. First packages are free.

Build a insulation & firestopping submittal free