Trade Submittal Guide

Flooring Submittal Template: What to Include and How to Build It

Quick Answer

A flooring submittal package (Division 09) is organized by the finish schedule: product data and physical samples for each flooring tag — carpet tile, LVT, resilient sheet, tile, wood, or resinous — plus the full installation system: adhesives, patching and self-leveling compounds, moisture mitigation, transitions, and base. Samples for architect approval and slab moisture testing requirements are what separate this package from a simple cut-sheet exercise.

What belongs in a flooring submittal package

Track the finish schedule tag by tag and include:

  • Product data per flooring type: construction, wear layer thickness (LVT), face weight (carpet), slip resistance (DCOF for tile), and fire test data where required
  • Physical samples in the specified size and quantity, labeled by tag and colorway — architect keeps a set
  • Adhesives and installation materials matched to the manufacturer's system, with the specified working-moisture limits
  • Moisture mitigation product and method where slab conditions or the spec require it
  • Patching/self-leveling compound data
  • Wall base, stair treads and nosings, and transition strips by location
  • Seaming diagrams for sheet goods and carpet where specified; pattern/dye-lot commitments for large areas
  • Maintenance instructions — commonly required with the package, not just at closeout

Moisture testing: the fight to have early

Most flooring failures — and most flooring disputes — trace to slab moisture. The spec will require RH testing per ASTM F2170 (or calcium chloride per F1869) with limits set by the flooring manufacturer. Put the testing protocol in your submittal, state who performs the tests, and submit the mitigation product you will use if slabs fail. Getting the mitigation system approved up front turns a two-week schedule crisis into a line-item change order — the alternative is arguing about an unapproved product while the schedule burns.

The review round-trip

Flooring packages go to the architect, and the physical samples drive the timeline: cut sheets can be approved in a normal cycle, but color and pattern selections often wait on an owner or designer decision. Submit samples in the first pass and chase them separately from the technical data. Expect 'Approved as Noted' with colorway confirmations, and hold ordering until dye lots are confirmed for anything with visible pattern matching.

Common rejection reasons on flooring submittals

Why flooring packages come back:

  • Samples missing, wrong size, or unlabeled against the finish schedule tags
  • Adhesive from a different manufacturer than the flooring system, voiding the warranty
  • No moisture testing plan or mitigation product where the spec requires one
  • DCOF or flammability data missing for the specified areas
  • Wall base and transitions omitted (they are in the section's submittal list more often than not)
  • Wear layer or face-weight below the specified minimum on a proposed 'equal'

How Submittal.App builds the flooring package

Give Submittal.App the finish schedule and the AI Builder assembles product data for each tag, keeps adhesives and accessories grouped with their systems, and generates a package with cover sheet and TOC that mirrors the schedule. Physical samples still travel by hand, but the paper side — usually a dozen manufacturers across one package — is done in minutes, and approvals feed your quotes and POs.

Related Questions

How many flooring samples do I need to submit?

The spec sets it — commonly two or three of each type, at a stated size (often 12"x12" or a full plank/tile). One set returns marked approved; the architect and owner keep the rest as the record standard.

What happens if the slab fails moisture testing?

You install the approved mitigation system — typically an epoxy moisture barrier — as an add. This is exactly why the mitigation product belongs in the original submittal: an approved product and unit price turns a failure into a same-week change order.

Are attic stock and maintenance materials part of the submittal?

The commitment is: specs usually require a percentage of overage per material. Note it in the package and carry it in your buyout, because closeout will require delivery tickets to match.

Do dye lots really matter for approval?

For large continuous areas of carpet or resilient, yes — the approved sample controls color, and a different dye lot at delivery can be rejected on site. Confirm lot reservations with the mill when quantities are large.