Trade Submittal Guide

Door Hardware Submittal Template: What to Include and How to Build It

Quick Answer

A door hardware submittal (08 71 00) is built around the hardware schedule: every opening on the door schedule, its hardware set, and each item in that set with manufacturer, model, function, finish and quantity. Behind the schedule go the cut sheets for every product, wiring diagrams for electrified openings, and a separate keying schedule. Fire-rated openings, accessibility and coordination with the frames, doors and access control are what reviewers check hardest.

📋 Download the free door hardware submittal checklist (printable PDF)

What belongs in a door hardware submittal package

Work from the door schedule, one opening at a time, and include:

  • Hardware schedule: each opening number, door and frame type, fire rating, hardware set number, and every item in the set with manufacturer, model, function, finish and quantity
  • Product data for every item: hinges, locksets and cylinders, exit devices, closers, stops, seals and thresholds, door pulls and plates
  • Finish designation for each item (BHMA code, e.g. 626 or 630), matched to the spec
  • Wiring diagrams for electrified openings — electric strikes, mag locks, power transfer hinges, request-to-exit and door position switches — showing the power supply and the connection to access control and fire alarm
  • Keying schedule as its own submittal, after the keying meeting with the owner
  • Templates for the door and frame makers, so lock, hinge and closer preps match
  • Fire-rated hardware listing for every rated opening, plus any certification the spec asks for (often from an Architectural Hardware Consultant)
  • Warranty and maintenance data where the section calls for it

Coordinate with the frames, doors and security first

Door hardware touches more trades than almost any other package. Hollow metal frames (08 11 13) and wood doors (08 14 16) are prepped from your templates, so the hardware submittal needs to be approved before their shop drawings can be finished. Electrified openings tie into access control (28 13 00) and fire alarm door release, so the wiring diagrams should match those packages. Send hardware early and sequence it with the doors, frames and security submittals — a late hardware package holds up all of them.

The review round-trip

Hardware packages usually go to the architect, sometimes to a hardware consultant, and the keying schedule goes to the owner. Expect comments on closer arms and mounting, lever trim, and functions that do not match the room use. Keying almost always takes its own round with the owner's facilities team, so start the keying meeting as soon as the hardware schedule is approved — cylinders and keys cannot ship until it is done.

Common rejection reasons on door hardware submittals

Why door hardware packages come back:

  • Hardware sets that do not match the door schedule — missing openings, wrong door numbers, or pairs treated as singles
  • Non-rated exit devices or hardware on fire-rated openings
  • Lock or exit-device functions that do not suit the room (for example, a classroom function where storeroom was specified)
  • Wrong finish, or mixed finishes on the same opening
  • No wiring diagrams for electric strikes, mag locks or power transfer hinges
  • Closers with the wrong arm type or mounting for the door swing
  • Hardware that fails accessibility rules — knobs instead of levers, or closers that exceed the opening-force limit

How Submittal.App builds the door hardware package

Give Submittal.App the door schedule and hardware sets and the AI Builder pulls the cut sheets for each item, groups them by hardware set, and generates the package with a cover sheet and table of contents that follows the schedule. The schedule itself stays yours, but the hours spent hunting down dozens of hinge, closer and lockset sheets are done in minutes.

Related Questions

Is the keying schedule part of the hardware submittal?

Usually it is a separate submittal. Most specs require a keying meeting with the owner after the hardware schedule is approved, then a keying schedule submitted on its own. Cylinders and keys are ordered only after that is approved.

Who prepares the door hardware schedule?

The hardware supplier, often through an Architectural Hardware Consultant on staff. Many specs require the schedule to be prepared or certified by one.

Why do the door and frame makers need the hardware submittal?

Doors and frames are prepped in the factory for the hinges, locks and closers. They use the hardware templates to cut those preps, so their shop drawings depend on the hardware being approved first.

Do electrified openings need extra documents?

Yes. Expect to submit wiring or riser diagrams for each electrified opening, showing power supplies, power transfer hinges and the links to access control and fire alarm. Reviewers reject packages that list the devices without the diagrams.