Trade Submittal Guide

Landscape Submittal Template: What to Include and How to Build It

Quick Answer

A landscape submittal package (Divisions 32 and 12/33 for related site work) covers plant material — a nursery list matching the plant schedule with species, caliper or container size, and source — plus soil mixes and amendments with lab analyses, mulch, irrigation system components from point of connection to heads and the controller, and hardscape and site-furnishing product data. Living material and seasonal windows make timing part of the submittal itself.

What belongs in a landscape submittal package

A complete landscape package usually spans:

  • Plant list keyed to the plant schedule: botanical name, quantity, size (caliper, height, or container), condition (B&B vs. container), and nursery source
  • Photos or certificates for specimen trees where the spec requires pre-tagging at the nursery
  • Topsoil and planting mix: source and a soils lab analysis against the specified gradation, pH, and organic content; amendment and fertilizer data
  • Mulch type and depth; edging and weed barrier
  • Irrigation: backflow preventer, controller (with any smart/EPA WaterSense requirement), valves, heads and nozzles with radius/precip data, drip components, pipe and wire
  • Hardscape unit pavers, sealers, and setting materials where in scope
  • Site furnishings and exterior lighting cut sheets where carried in your contract
  • Maintenance and establishment-period plan when the spec lists it as a submittal

Plant material: substitutions are the norm, so document them

Nursery availability shifts season to season, and landscape architects know it — but they still control the palette. When a specified species or size is unavailable, submit the substitution formally with the proposed species, size, and source, rather than shipping what the nursery had. Size substitutions cut both ways: larger material is not automatically acceptable (transplant shock, budget) and smaller material needs the LA's sign-off in writing. For projects with specimen trees, get the LA to tag trees at the nursery and record the tagging in the submittal file.

The review round-trip

Landscape packages route to the landscape architect, with civil weighing in on irrigation points of connection and the backflow preventer (which the local water authority may also need to approve). Reviews are usually reasonable in speed, but the calendar is the real reviewer: plant approval has to land far enough ahead of the planting window that the nursery can hold or grow the material. Submit the soil analysis early too — failed soil tests cascade into import/export changes that touch the schedule and the budget.

Common rejection reasons on landscape submittals

Where landscape packages get bounced:

  • Plant sizes below schedule (2" caliper submitted against a 2.5" schedule) or container sizes swapped without approval
  • Soil submitted without a current lab analysis, or an analysis that misses the specified gradation and organic content
  • Irrigation heads with precipitation rates mismatched within a zone
  • Backflow preventer model not on the local jurisdiction's approved list
  • Controller missing specified smart features (flow sensing, weather-based adjustment)
  • No source identified for plant material, making pre-tagging impossible

How Submittal.App builds the landscape package

Submittal.App's AI Builder assembles the manufactured side of the package — irrigation components, furnishings, lighting, hardscape products — from indexed cut sheets in minutes, and organizes plant lists and soil reports you attach into the same coherent package with cover sheet and TOC. One link to the GC for review, and approved items feed quotes and purchase orders directly.

Related Questions

When should plant material submittals go in relative to planting season?

Early enough that approval lands one growing season's procurement ahead of the planting window — for spring planting, that usually means submitting in fall or early winter so nurseries can allocate or contract-grow material.

Who approves the irrigation backflow preventer?

The landscape architect or civil engineer approves it in the submittal, but the local water purveyor must also accept the model and installation — check their approved list before you submit, not after.

What does a soil analysis submittal need to show?

A recent lab report on the actual source material covering gradation, pH, organic matter, and soluble salts against the spec's ranges, plus the amendment recommendations. A supplier's generic data sheet is not an analysis.

Is the landscape establishment period a submittal item?

Frequently — specs require a maintenance/establishment plan (watering, mowing, replacement policy) covering 90 days to a year after substantial completion. Submitting it up front sets the warranty clock cleanly.