Lighting Submittal Template: What to Include and How to Build It

Quick Answer

A lighting submittal package is organized around the fixture schedule: one cut sheet per type (A, B, C…) with the exact catalog number built out — lumen package, CCT, CRI, voltage, driver, mounting, and finish all marked. Add photometric files where specified, emergency battery or inverter data, and the lighting controls package with device layouts and a sequence of operations. It is reviewed by more parties than almost any other submittal, so precision on options matters.

What belongs in a lighting submittal package

Lighting sits in 26 51 00 (interior), 26 56 00 (exterior), and 26 09 23 / 26 09 43 for controls. The package should contain:

  • A cut sheet for every type on the fixture schedule, in schedule order, tagged with the type letter
  • Full catalog logic decoded: lumen output, CCT, CRI, voltage, driver type (0-10V, DALI, DMX), options, and finish
  • Photometric data (IES files or summary tables) when the spec or designer requires it
  • Emergency lighting: battery packs, inverters, or generator-transfer devices with runtime and listing data
  • Poles and bases for exterior fixtures, with EPA and wind-load data
  • Controls: occupancy/vacancy sensors, dimmers, relay panels, network devices, plus a sequence of operations and zoning plan where specified

Decode the catalog number completely

Most lighting rejections happen inside the catalog string. A modern LED fixture ordering code can run twenty characters — lumen package, distribution, CCT, voltage, driver, dimming protocol, options, finish — and the reviewer needs to see every position resolved. Submitting the family page with the ordering matrix untouched forces the reviewer to guess, and reviewers do not guess; they write 'Revise and Resubmit.' Mark the exact string being furnished, and confirm the dimming protocol matches the controls system on the drawings.

The review round-trip

Lighting packages typically pass through more hands than other trades: GC, electrical engineer, architect, and on design-forward jobs a lighting designer with strong opinions about substitutions. Expect the full review window and expect aesthetic comments, not just technical ones. Package alternates and substitutions separately with a substitution request — burying an 'or equal' inside the schedule order is the fastest route to a full-package rejection.

Common rejection reasons on lighting submittals

The classics:

  • Catalog number incomplete or ordering matrix unmarked
  • Wrong CCT or CRI versus the schedule (3500K submitted against a 3000K schedule)
  • Dimming driver that doesn't match the control system protocol
  • Substituted fixture without photometrics proving equivalent distribution
  • Missing emergency listing (UL 924) on egress fixtures
  • Exterior fixtures without the specified finish or without pole EPA calculations

How Submittal.App builds the lighting package

Lighting is Submittal.App's home turf: the library indexes hundreds of thousands of fixture cut sheets across major lighting brands. Paste the fixture schedule and the AI Builder matches each type to the right document, assembles the package in schedule order with a cover sheet and TOC, and flags any type it cannot confidently match. Approved packages flow straight into quotes and POs with the catalog numbers intact — and when the designer swaps Type F3 in review, rebuilding the corrected package takes minutes instead of another evening.

Related Questions

Do lighting controls go in the same package as fixtures?

Usually as a companion package under 26 09 23/43. Fixtures can be released while controls sequences are still in review, but the dimming protocol must be locked across both — that is the coordination point reviewers check hardest.

What are IES files and when do I need to submit them?

Photometric data files describing a fixture's light distribution, used to verify light levels in calculation software. Submit them when the spec requires photometrics or when you propose a substitution — they are how the designer verifies equivalence.

How are fixture finishes and custom colors handled?

Standard finishes are called out in the catalog string. Custom RAL colors usually require a physical or digital color sample for architect approval and add weeks of lead time, so submit them first, not last.

Why did my package get comments from the architect and the engineer?

Lighting is jointly owned: the engineer reviews electrical characteristics, emergency function, and code compliance while the architect or lighting designer reviews appearance, CCT, and distribution. Both sets of comments must be resolved before release.