Electrical Submittal Template: What to Include and How to Build It

Quick Answer

An electrical submittal package covers the Division 26 spec sections on your scope: product data (cut sheets) for gear, devices, conduit, and wire; shop drawings for switchboards, panelboards, and anything custom-fabricated; and supporting items like short-circuit and coordination studies where specified. Organize it by spec section with a cover sheet and transmittal, and submit early — electrical gear lead times are often the longest on the job.

What belongs in an electrical submittal package

Start from the specs, not from memory. Each Division 26 section has a Part 1 'Submittals' article that lists exactly what the engineer expects. On a typical commercial job you will be pulling submittals for most of these sections:

  • 26 05 19 — Wire and cable: manufacturer cut sheets with conductor type, insulation rating, and temperature rating flagged
  • 26 05 33 — Raceways and boxes: conduit, fittings, and box product data
  • 26 24 13 / 26 24 16 — Switchboards and panelboards: shop drawings with bus ratings, AIC ratings, breaker layouts, and dimensions
  • 26 27 26 — Wiring devices: receptacles, switches, cover plates, with finishes noted
  • 26 28 16 — Enclosed switches and circuit breakers
  • 26 51 00 — Lighting (often handled as its own package with the fixture schedule)
  • Studies where specified: short-circuit, coordination, and arc-flash — usually a deferred or separate submittal

Product data vs. shop drawings for electrical

For catalog items — devices, conduit, wire, disconnects — a marked-up manufacturer cut sheet is enough. Highlight the exact catalog number, voltage, and options being furnished, and strike or cloud everything that does not apply. A cut sheet with six unmarked variants is the fastest way to get 'Revise and Resubmit.'

Gear is different. Switchboards, panelboards, and MCCs need factory shop drawings: one-line, elevation, bus arrangement, breaker schedule matched to the panel schedule on the drawings, and nameplate data. The engineer reviews these against the load calcs, so mismatched breaker frame sizes or AIC ratings get caught immediately.

The review round-trip

The package goes from you to the GC, who logs it and forwards to the electrical engineer of record. Expect 10 business days of review time per the general conditions, plus the GC's handling time on both ends — call it two to three weeks door to door. Gear submittals often come back 'Approved as Noted' with corrections to breaker sizes or feeder designations; you incorporate the notes and release for fabrication without resubmitting unless the stamp says otherwise.

Common rejection reasons on electrical submittals

The same handful of problems cause most electrical rejections:

  • AIC ratings on panelboards lower than the fault current shown in the study
  • Unmarked cut sheets — reviewer cannot tell which catalog number is being furnished
  • Substituted gear manufacturer without a substitution request when the spec is proprietary
  • Missing series ratings documentation when breakers are series-rated
  • Fixture or device finishes that ignore the architect's finish schedule
  • Wire submitted at 75°C when terminations require 90°C rated conductors

How Submittal.App builds the electrical package

Submittal.App's AI Builder reads your schedule or spec section, matches each catalog number against an indexed library of manufacturer cut sheets, and assembles a formatted package — cover sheet, table of contents, and section dividers — in minutes. You review, adjust, and send a link to the GC instead of spending an evening merging PDFs. When the review comes back, the approved package converts straight into quotes and purchase orders.

Related Questions

Should lighting be a separate submittal from electrical gear?

Usually yes. Lighting (26 51 00) has its own reviewer chain — the lighting designer or architect weighs in alongside the engineer — and its own lead times. Splitting it keeps a fixture comment from holding up your switchgear release.

When should electrical submittals go in on a project?

Gear first, and as early as possible — switchboard and panelboard lead times of 20-40+ weeks are common, and fabrication cannot start until the shop drawings are approved. Devices, wire, and conduit can follow on the normal schedule.

Do I need to submit on wire and conduit if they're commodity items?

If the spec section lists them under submittals, yes. Engineers use the wire submittal to verify insulation type and temperature ratings, and the conduit submittal to confirm materials in corrosive or exterior locations. It is a cheap submittal to prepare — skip it and it becomes a punch-list argument later.

What is a series rating and why does it get flagged?

A series rating lets a downstream breaker with a lower AIC rating be protected by an upstream device, as a tested combination. Reviewers flag it because the combination must be UL-listed and documented — you have to submit the manufacturer's series rating tables, not just the breaker cut sheets.